Quick answers
The NEC is the National Electrical Code: its rules are mandatory when they use "shall" and permissive when they use "shall be permitted," and its scope is set by Article 90.
- What is the difference between mandatory and permissive rules in the NEC?
- Mandatory rules identify actions that are specifically required or prohibited and are characterized by the terms "shall" or "shall not." Permissive rules identify actions that are allowed but not required, describe options or alternative methods, and are characterized by the terms "shall be permitted" or "shall not be required." (NEC 90.5)
- What installations does the NEC cover?
- NEC 90.2(A) covers the installation of electric conductors, equipment and raceways, and optical fiber cables, for six categories: public and private premises (buildings, structures, mobile homes, recreational vehicles and floating buildings); yards, lots, parking lots, carnivals and industrial substations; installations of conductors and equipment that connect to the supply of electricity; electric-utility installations that are not an integral part of a generating plant, substation or control center; installations supplying shore power to ships and watercraft in marinas and boatyards; and installations used to export electric power from vehicles to premises wiring. Treat the lists as closed — the items are cited as 90.2(A)(1) through 90.2(A)(6). (NEC 90.2(A))
NEC 90 — Introduction (Washington Journeyman)
Learning Objectives
1.1 Article 90.1 — What Article 90 Covers
Section 90.1 states that Article 90 covers the use and application, arrangement, and enforcement of the code, the expression of mandatory, permissive, and nonmandatory text, guidance on the examination of equipment and on wiring planning, and the use and expression of measurements.
Scope is 90.2, arrangement is 90.3, enforcement is 90.4, code text is 90.5, equipment examination is 90.7, wiring planning is 90.8, measurements are 90.9. Distractors claim that 90.1 lists all permitted equipment or gives design specifications for untrained persons.
1.2 90.2(A)(1) — Covered Installations and Locations
The code covers the installation and removal of electrical conductors, equipment, and raceways; signaling and communications conductors, equipment, and raceways; and optical fiber cables, for six categories:
Treat every list as closed: airports and railroad yards are not in the yards-and-lots list, and marinas and boatyards appear only in the shore-power category. Questions cite these items as 90.2(A)(1) through 90.2(A)(6) — yards and lots as 90.2(A)(2), supply connections as 90.2(A)(3), utility buildings as 90.2(A)(4), shore power as 90.2(A)(5).
1.3 90.2(A)(2) — Installations Not Covered
The same section that grants coverage also withdraws it. The code does not cover:
Floating buildings stay covered while other watercraft are excluded, and mobile homes and recreational vehicles stay covered while other vehicles are excluded.
1.4 90.2(B) — Practical Safeguarding: the Purpose of the Code
The purpose of the code is the practical safeguarding of persons and property from hazards arising from the use of electricity. The same paragraph adds the limitation behind many questions here: the code is not intended as a design specification or an instruction manual for untrained persons.
It is a minimum safety standard for installation and maintenance, not a design manual or engineering reference. Distractors invert the sentence and call it a design specification for untrained persons.
1.5 90.2(C) — Adequacy: What Compliance Does Not Guarantee
The code contains provisions considered necessary for safety. Compliance with them, together with proper maintenance, results in an installation that is essentially free from hazard — but not necessarily efficient, convenient, or adequate for good service or future expansion of electrical use.
The Informational Note explains why: hazards often occur because of overloading of wiring systems by methods or usage not in conformity with the code, and this occurs because initial wiring did not provide for increases in the use of electricity.
1.6 90.2(D) — Relation to Other International Standards
The requirements of the code address the fundamental principles of protection for safety contained in Section 131 of International Electrotechnical Commission Standard 60364-1 — protection against electric shock, thermal effects, overcurrent, fault currents, and overvoltage. IEC rules are not what an inspector enforces.
1.7 90.3 — Code Arrangement: Nine Chapters in Two Layers
The code is divided into the introduction and nine chapters, as shown in Figure 90.3.
| Layer | Content | How it applies |
|---|---|---|
| Chapters 1 through 4 | Wiring and protection, wiring methods, equipment for general use | Apply generally to all electrical installations |
| Chapters 5 through 8 | Specific occupancies and locations, equipment, conditions and systems, communications | May supplement or modify the requirements in Chapters 1 through 8 |
| Chapter 9 | Tables | Applicable as referenced |
| Informative annexes | Nonmandatory information | Informational only; not part of the requirements |
Chapters 5 through 8 may supplement or modify the requirements in Chapters 1 through 8, so this is not a hierarchy in which the general chapters always win: a Chapter 5 rule can change what a Chapter 3 wiring method would require.
1.8 90.4 — Enforcement: Application, Interpretations, Special Permission, New Products
The authority cannot delete an article, convert a mandatory rule into a permissive one, or delegate enforcement to the installing contractor, and the contractor, manufacturer, laboratory, and NFPA technical committee hold no interpretation authority.
1.9 90.5 — Mandatory Rules, Permissive Rules, and Explanatory Material
Unless a reference to a publication includes a date or edition, the reference is to be considered the date or edition contained in Informative Annex A, not automatically the most recent edition. A shall be permitted sentence offers an option you may use; a shall sentence in the same article still binds you.
1.10 90.6 through 90.9 — Interpretations, Examination, Planning, Units
1.11 Washington Practice and Open-Book Navigation
Washington administers electrical licensing through the Department of Labor & Industries and adopts the National Electrical Code statewide with amendments: an amendment governs the field installation, while the examination uses the edition provided in the room.
Code Navigation
| Topic | NEC Section | What it covers |
|---|---|---|
| Article 90 scope | 90.1 | Use, application, arrangement, enforcement, code text, examination, planning |
| Covered installations | 90.2(A)(1) | Premises, yards and lots, supply connections, non-integral utility buildings, shore power |
| Not covered | 90.2(A)(2) | Ships and watercraft, rolling stock, aircraft, other vehicles, mines, exclusive utility installations |
| Purpose | 90.2(B) | Practical safeguarding; not a design specification for untrained persons |
| Adequacy | 90.2(C) | Free from hazard, not necessarily efficient or adequate for future expansion |
| Code arrangement | 90.3 | Chapters 1 through 4 general; Chapters 5 through 8 supplement or modify; Chapter 9 tables |
| Enforcement application | 90.4(A) | Mandatory application by governmental bodies or insurance inspectors |
| Interpretations | 90.4(B) | AHJ interprets rules, approves equipment, grants special permission |
| Special permission | 90.4(C) | Waiver or alternative methods where equivalent safety is assured |
| New products | 90.4(D) | Products complying with the most recent previous edition adopted |
| Rule types | 90.5(A), 90.5(B) | Shall and shall not; shall be permitted and shall not be required |
| Explanatory material | 90.5(C), 90.5(D) | Notes and annexes not enforceable; undated references follow Annex A |
| Units | 90.9 | SI first, inch-pound in parentheses, hard and soft conversion |
Common Exam Traps
Practical Field Points
Summary
Article 90 fixes the frame in which every other rule operates. Section 90.1 declares what the article covers: use and application, arrangement, and enforcement, plus the expression of mandatory, permissive, and nonmandatory text, examination of equipment, wiring planning, and measurements. Section 90.2 sets document scope in two halves: 90.2(A)(1) lists the covered installations and locations, from premises and yards to marinas and vehicle-to-premises power export, while 90.2(A)(2) excludes ships and other watercraft, rolling stock, aircraft, other vehicles, mines, exclusive railway and communications installations, and utility service drops and easement installations. Section 90.2(B) makes practical safeguarding the purpose and rejects any reading of the code as a design specification or instruction manual for untrained persons, and 90.2(C) limits compliance to an installation essentially free from hazard, not necessarily efficient, convenient, or adequate for good service or future expansion. Section 90.3 arranges the code into nine chapters, with Chapters 5 through 8 supplementing or modifying Chapters 1 through 8 and Chapter 9 tables applying as referenced. Section 90.4 assigns enforcement, interpretations, approval of equipment, and special permission to the authority having jurisdiction, and permits products of the previous adopted edition where newly required ones are not yet available. Section 90.5 separates shall rules from shall be permitted rules and from nonenforceable explanatory material, and 90.6 through 90.9 close the article with formal interpretations, equipment examination, wiring planning, and units. Learn these pages first: they are the shortest path to every other answer in the book.
Preparing for the Washington journeyman license?
See the full licensing path, exam format, eligibility and application steps.
Ready to test this chapter?
Practice with exam-aligned questions and timed simulations.
Start Practicing Free